I work in the sector and it's impossible to build a full-sized reactor in less than 10 years, and the usual over-run is 5 years. That's the time for tried and tested designs. The tech isn't there yet, and there are no working analogs in the US to use as an approved guide. The Department of Energy does not allow "off-the-cuff" designs for reactors. I think there is only two SMRs that have been built, one by the Russians and the other by China. I'm not sure they are fully functioning, or at least working as expected. I know there are going to be more small gas gens built in the near future and that SMRs in the US are way off.
ericd|1 year ago
perryizgr8|1 year ago
I'm curious why that is. If we know how to build it, it shouldn't take that long. It's not like we need to move a massive amount of earth or pour a humongous amount of concrete or anything like that, which would actually take time. Then why does it take 15 years to build a reactor with a design that is already tried and tested and approved?
jscottbee|1 year ago
One of the big issues that have occurred (in the US especially) is, that for 20+ years there were no new plants built. This caused a large void in the talent pool, inside and outside the industry. That fact, along with others has caused many problems with some projects of recent years in the US.
mullingitover|1 year ago
When you're the biggest fossil fuel producer in the world, it's vital that you stay laser-focused on regulating nuclear power to death in every imaginable detail while you ignore the vast problems with unchecked carbon emissions and gaslight anyone who points them out.
unknown|1 year ago
[deleted]
cbozeman|1 year ago
112 reactors.
A gigawatt each.
Over 10 years ago.
jscottbee|1 year ago
JumpCrisscross|1 year ago
We’re not doing time and tested.
> Department of Energy does not allow "off-the-cuff" designs for reactor
Not by statute!
twelve40|1 year ago
> there are no working analogs in the US to use as an approved guide
small reactors have been installed on ships and submarines for over 70(!) years now. Reading up on the very first one, USS Nautilus, "the conceptual design of the first nuclear submarine began in March 1950" it took a couple of years? So why is it so unthinkably hard 70 years later, honest question? "Military doesn't care about cost" is not good enough, there are currently about >100 active ones with who knows how many hundreds in the past, so they must have cracked the cost formula at some point, besides by now we have hugely better tech than the 50's, so what gives?
jscottbee|1 year ago