throwaway422432 | 4 months ago
Ball park for a processing plant is 1.5b and 2-3 years from digging foundations to operations if the funds are there and it's fully approved. A lot of the metallurgical testing can be done in parallel with the build, but getting off-take partners requires being able to prove you can supply, and the off-take partners usually supply a lot of the funding.
Case in point, Lynas' Seadrift project in Texas is stalled and may not proceed due to an waste-water permitting issue and the USG not wanting to provide the additional funding required, or fully commit and guarantee off-take.