ecaradec | 2 months ago

When working with kanban I maintained a average number of card done per days. if someone asked when some card woud be done, I just multiplied the number of card ahead of that one by average and get an estimate. You can estimate the cards but usually it doesnt really improve accuracy as tasks are on average the same size.