Connections to HS1/Europe, and to Leeds, Golborne, East Midlands, Manchester and finally even Crewe have all been cancelled so now extra expenditures will focus instead on Euston Station. That's not the large section people were interested in riding. Perhaps Old Oak Common should instead have been tunnelled the same distance through to Waterloo International (whose international platforms are now deleted).
kruador|27 days ago
The extension to Euston was supposed to have 11 platforms. Even the reduced scope now being implemented is 6 platforms, I believe. All 11 were required to handle the eastern leg of HS2 [providing bypass capacity for the East Coast Main Line out of King's Cross and the Midland Main Line out of St Pancras], and services to Scotland and Manchester [bypassing the West Coast Main Line from Euston's classic platforms].