top | item 47147635

You Can't Buy a Data Center

22 points| anujsharmax | 6 days ago |timlig.com

4 comments

order

gdevillers|5 days ago

Will we see people being paid to host small single-GPU servers in their home ? I guess that would require redesigning the training system because the data transfer speed would be much slower with a higher latency. Maybe that is not even compatible with LLM training ?

7777777phil|5 days ago

128 to 210 WEEKS for power transformers. You can fab more GPUs in 18 months but the electrical infrastructure to run them takes 3-4 years and there are maybe a handful of manufacturers. Feels like the stories from the telecom fiber overbuild of 2000 except this time the supply chain can't even overbuild if it wanted to.

ekropotin|5 days ago

I miss good’ol pre-LLM days so much